An international shipping company opened a new 24x7 customer service center to support its US customer base. To maximize uptime and ensure high reliability, a redundant UPS system was installed, protecting both the supply and the facility loads. Integral to the facility design was the Encore Series power monitoring system from Dranetz installed on the input and output of these UPS systems. The Encore Series provides real-time access to all power monitoring information using a standard web browser. This feature was quite important to the nationwide facility manager who travels frequently and required remote access to the facility’s infrastructure regardless of his physical location. He also needed a system that allowed multiple facility personnel from around the world to review system data, view trends to prevent future problems and remedy any inconsistencies.
Within a mere few months, the Encore Series provided valuable information to ensure power reliability at this critical facility. Most important, the system verified the expected performance of the UPS system and detected no disturbances on the UPS output feeding the critical loads (figure 1). However, monitoring the incoming power from the utility supply indicated more than 50 disturbances in the first three months of operation (figure 2). These disturbances included sags and transients that could have impacted unprotected loads, seriously compromising power reliability. Armed with the data, the facility manager contacted the utility who was able to pinpoint the problem as a faulty relay. The problem was corrected, while the Encore Series system continues to provide proactive information to support the uptime needs of the facility.


Thursday, February 20, 2014

Encore Series System Solves Hospital's Power Outage Problem

By monitoring the incoming and outgoing power from a UPS supplying critical power to the Cath Lab X-Ray System and using the cross triggering comparison feature, the Encore Series instrument (at the time, this instrumentation was referred to as 'Signature System') was able to pinpoint the power outage problem.

The Encore verified the interruption of the utility supply and that the UPS was doing its job, providing a "clean" supply of power to the load. However, twenty seconds passed before the emergency generator came on-line, causing downtime and confusion. The Encore data enabled the customer to determine that the X-ray Emergency Power Off switch was being incorrectly fed directly by emergency power, rather than feeding the UPS as was specified in the hospital’s power system design.

Wednesday, February 12, 2014

Case Study: Stalled Motors


In this case study, we look at an industrial customer with two 1250 hp motors on a 4kV circuit, whose motors would not start. To determine the problem, we installed a Dranetz PowerGuide 4400 at the motor input. The power monitoring instrument quickly identified the motor itself as the source of the problem. In fact, the motor start caused a deep sag to occur, which impacted the motor control circuitry and stopped the motor from starting. In effect, the motor was "shooting itself in the foot," creating a cycle of non-performance.
The customer was presented with several mitigation options, including adding more capacity to the circuit, installing a constant voltage transformer, or installing an uninterruptible power supply (UPS) system. The customer selected the UPS option, which was installed to protect the motor control circuitry during motor start-up and verified using the PowerGuide 4400.
Inrush currents, such as those associated with motor starting can cause interaction problems with other loads. When motors are started they typically draw 6-10 times their full load, which can cause voltage sags. These events can dim lights, cause contactors to drop out, disrupt sensitive equipment, and as in our case study, affect the successful start of a motor. The use of a power quality monitor that can capture waveforms during long duration start-ups will be quite effective in characterizing and optimizing motor starts.

Tuesday, January 7, 2014

Data Center Uptime


In today’s 7x24 uptime world, a power outage begins after four milliseconds and can cost millions of dollars a year in downtime. Minimizing the probability of that impact requires facility managers to fully understand their power system infrastructure so they can maximize power reliability and quality. And while most data centers have invested in power Power monitoring is key to maximizing uptime and ensuring all power infrastructure is functioning properly.
mitigation technologies such as UPS and backup generation technologies, a 7x24 operation needs continuous power information to ensure that these systems are delivering highly reliable, clean power. 
Handheld and Portable Instruments: Typically used for troubleshooting or forensic investigation of power quality problems, these instruments can be brought into the field and used to collect information on an as-needed basis. Dranetz’s weather-resistant packaging enables users to leave instruments in the field for long-term monitoring and studies.
Permanently Installed, Continuous Monitoring Systems: The continuous capture of power quality and energy data puts facility managers in a position to proactively manage their power infrastructure, by increasing their knowledge and giving them the tools to increase system reliability.
Power Quality Software: Interpreting power monitoring data can be an overwhelmingly complex and time-consuming task. Dranetz prides itself on having the most user-friendly power quality software on the market.

Friday, July 19, 2013

Hospital's Power Outage Problem Solved


By monitoring the incoming and outgoing power from a UPS supplying critical power to the Cath Lab X-Ray System and using the cross triggering comparison feature, the Encore Series instrument (at the time, this instrumentation was referred to as 'Signature System') was able to pinpoint the power outage problem.
The Encore verified the interruption of the utility supply and that the UPS was doing its job, providing a "clean" supply of power to the load. However, twenty seconds passed before the emergency generator came on-line, causing downtime and confusion. The Encore data enabled the customer to determine that the X-ray Emergency Power Off switch was being incorrectly fed directly by emergency power, rather than feeding the UPS as was specified in the hospital’s power system design.